Updates
The masonry work is all but done - pending inspection today. They have a little more minor groutwork to finish but it looks good.
The plumbing is backed up in the kitch and laundy. Esteban is coming out today to snake the shit out of it.
I met w/ Rich from Cactus Garage Doors (www.cactusgaragedoors.com) today. We either have to lower the new opening to 6'6" or remove the old beam and replace it with one that will give us the needed 8' or so of clearance with the new opening.