Electrical Update
Mike came by this morning and said he will be out on Sunday to do the kitchen wall. He suggested we don't order countertops until the cabinets are in place because it is such a precise measurement that can change as the cabinets go in. I think he is right. When we order the counters we should hire HD to install them so they will come out and measure them so any errors will be on their shoulders. SO we should probably go ahead and get the cabinets delivered so Kevin can get started after Sunday. The only thing he is waiting for is Mike to finish so he can drywall the kitchen wall and start demo. Mike said he will run a temp light into the garage for us. I hate not having light in there. I told him we ordered the outdoor lighting. Mike also agreed all new duct work is a good idea. He did say that over several years the flex tube will dry out and crack but it should be fine if we don't bump it or move it so we will just have to keep that in the back of our mind.